A global tech company needed assistance setting up the comms room for their new Paris office.
Our team installed 2 x 4-post Chatsworth Racks, with horizontal and vertical Panduit cable management systems, just as the last Cat6 a cable had been pulled into the room, allowing the local contractor to terminate into the rack without any delays.
Once the fit-out was complete (clean site) our engineer returned to install the routers, firewalls, network switches and Wireless Access Points throughout the office space (20,000 sq ft) and provided hands on assistance to help their US based network team get the site online.







All works were completed on time, site go live date was completed 2 weeks before the office opened allowing their workspace/facilities team to be onsite to make the space ready for their staff and official office opening date.
Contact us today for a free consultation or site survey.